Pasmangoor road access construction

Contract Date:

2009

عنوان مقدار
ClientNuclear Industry Waste Management Company of Iran
AdvisorIran Industrial Consulting Engineers Company
Contract Period15 months + 60 months (maintenance period)
LocationAnarak
StatusFinished

Description

Brief Description: Anarak-Pasmangoor site 21-km asphalted access road was constructed to link Pasmangoor site to Iran’s national roads network. The project consisted of a wide range of operations, including excavation, construction of technical buildings, walls, and bridges, street gutters, parapets, and installation of traffic signs.

The project was aimed at developing the nuclear waste management industry and achieving self-efficiency in the field of nuclear waste management.

Scope of Work

  • Excavation based on the longitudinal and cross-section profiles and reaching the code points
  • Construction of all technical buildings (walls, bridges, street gutters, and canals
  • Construction and installation of all the required safety signs, guard rails, and parapets
  • Construction of all minor road entrances and exits

Key Statistics

  • Excavation in earthy and rocky terrains, and explosion-prone areas, 850,000 m3
  • Asphalt paving, 34,000 m3
  • Sub-base construction, 35,000 m3
  • Base construction, 28,000 m3
  • Metal formwork, 14,000 m2
  • Rebar binding and other metalwork, 120,000 kg
  • Concreting, 10,000 m3